LYSANDER ROW BREAKS GROUND
11/11/ 2026

After considerable time and effort, we’re excited to announce the first phase of “12th & Forest” broke ground on November 9th, 2026.



Lysander Row, a 4-unit townhouse development located at 1758 Lysander has secured construction funding, all necessary permits and commence construction earlier this week.  The build-out is expected to take 9 months, with completion in Summer 2027.  To keep the community in-the-loop, we’ll be posting regular progress announcements here, so stay tuned!  The first month of construction will include site preparation, erosion control measures, and utility trenching.  December is scheduled for underground plumbing, concrete foundations and slab work.

Our goal is to build a supremely high-quality structure, with an minimal disruption to the neighborhood throughout construction, so please reach out with any questions or concerns!






—